Engineering Documentation in Pharmaceutical Industry
- Heat Load Calculations.
- AHU Zoning drawing with pressure differentials.
- Airflow diagram.
- Ducting layout.
- Piping Layout.
- HEPA Box G.A.
- Man Movements layout
- Material Movements layout
- The layout of Pressure difference and area classification in production
- Area Qualification
- Area Mapping
- Commissioning Report of HVAC System
- Airflow & ACPH (Room wise)
- Filter Integrity (PAO) for All AHU
- Non-Viable Particle Count for All AHU
- HEPA filter Certificate
- Recovery Study Report (Room wise)
- Filter Certificates (HEPA, 05 microns & 10 Micron)
- Purchase Order
- Plant Layout Floor wise (Production)
- Plant Layout Floor wise (Warehouse)
- Plant Layout (General)
Water System
- Purchase Order
- MOC Certificate of Water Distribution Line and Purified Water Plant
- Welding Certificate of Joint
- Baroscopic Photo of Pipeline
- Dead Leg Certificates of sampling point and pipework
- DQ, IQ and OQ Protocol
- Schematic Diagram of water System showing all equipment in the system from the inlet to the points of use along with sampling points
- Approved piping drawings (e.g. orthographic and/or isometric)
- Commissioning Report of water System
- Calibration Certificate of All instruments used in the water System – ( like – Pressure Gauge, Flow meter, Temperature Sensor)
- Slopes certificates of Pipeline
Tags
Engineering